Concrete Slab vs. Footers for a Metal Building: Which Do You Need?

Interior of a steel building before the slab is poured

Written by

in

· Updated

Before a steel building goes up, it needs something solid to sit on and anchor to. The two words you will hear most are footers and slab. They are not the same thing, and plenty of buildings use both. Since we pour the concrete and install the building ourselves, here is how we explain it to customers.

Cross-section diagram comparing a footer below the frost line plus a 4-inch slab with a thickened-edge monolithic slab for a metal building
A: footer below the frost line plus a 4-inch slab. B: thickened-edge slab. Diagram: Stoots Storage Solutions.
Footer trench with rebar set inside the forms, laser level in the background
Footer trench with rebar, dug and formed before the slab pour.

What footers do

Footers (also called footings) are concrete poured in trenches under the building’s legs or perimeter. Their job is to carry the weight of the structure and give the anchors something deep and solid to hold onto. Footers have to go below your area’s frost line, so the ground freezing and thawing in winter does not heave the building.

What a slab does

A slab is the flat concrete floor. For most garages, shops and storage buildings, we pour a 4-inch slab. It gives you a clean, dry floor to park on, roll equipment across or set up a workshop.

Common setups

  • Footers plus a slab: the most common setup for an enclosed garage or shop. The footers carry the building, and the slab is your floor.
  • Footers only: works for carports, ag buildings or barns where you want a gravel or dirt floor, or plan to pour the floor later.
  • Slab only: some smaller buildings can anchor straight to a properly built slab with thickened edges. Whether that is allowed depends on the building, the loads and your county.

How to decide

Ask yourself three questions. What will be inside: vehicles, equipment, livestock or hay? Do you need a finished floor now, or can it wait? And what does your county require for the size and use of the building? Your building’s engineered drawings and local code decide the minimum. We will tell you what applies to your site.

What the Virginia code says

Virginia’s 2021 Residential Code sets the floor for homes and residential accessory buildings like garages. Your building’s engineered drawings and your local building official can require more.

  • Footers go below the frost line. Section R403.1.4.1 says foundations have to be protected from frost, usually by extending below the frost depth your locality sets. There are exemptions for small free-standing accessory buildings with an eave height of 10 feet or less: up to 600 square feet for light-frame construction, or 400 square feet for other construction. Ask your building office how they classify a metal building before you count on it.
  • Slabs are at least 3½ inches thick. Section R506.1 sets the minimum. A 4-inch slab is what we pour for most garages and shops.
  • Vapor retarder under heated slabs. Section R506.2.3 of Virginia’s 2021 Residential Code calls for a 10-mil vapor retarder under slabs, with an exception for garages, carports and other unheated accessory buildings. If there is any chance you will heat or finish the building later, put it in now. You cannot add it after the pour.

Frost depth around Southwest Virginia

LocalityPublished frost depthSource
City of Galax18 in.City design criteria (2025)
Town of Tazewell18 in.Town design criteria
Pulaski County12 in. minimum for 256–600 sq ft buildings; deeper for larger buildingsAccessory structure guide

Your county may be different. Our frost depth guide covers more localities and how frost depth works.

Separate footers vs. a thickened-edge slab

Footers plus a slab (drawing A) carry the building on concrete that goes down below the frost line, with the slab poured as the floor. It is the most common setup for enclosed garages and shops, and the one most counties expect for larger buildings.

A thickened-edge slab (drawing B), also called a monolithic or turned-down slab, pours the floor and a deeper edge in one shot. The building anchors into that edge. It can save a pour on the right job, but only where the building’s drawings and your building office allow it.

Control joints and cracking

Concrete shrinks as it cures, and it will crack somewhere. Control joints give it a straight line to crack along. A common rule of thumb is to space joints two to three times the slab thickness in feet, so roughly every 8 to 12 feet on a 4-inch slab, and to keep the panels close to square. We lay the joints out around the building, the doors and how you will use the floor.

Give the concrete time

Concrete keeps gaining strength for weeks after it is poured, and keeping it moist early on helps it get there. Anchors and the building go on when the concrete is ready for them, which is one more reason to have one company scheduling both. Here is how long concrete should cure before a metal building goes up.

Why one crew for both matters

When one company pours the concrete and a different company sets the building, small measurement problems turn into finger-pointing. The building has to land on the anchors exactly. Because we do both, the slab is poured to fit your building’s exact layout, and there is one phone number to call if anything is off.

How concrete is paid

Concrete is quoted separately from the building. 10% of the job subtotal is due at signing, 35% of the remaining balance at the footer pour, and the last 65% when the 4-inch slab is poured. See our concrete and foundations page for more.

Not sure if you need a slab or footers? We do grading and concrete too. Call or text 276-235-1191, or send us a quote request.

Ready to price your own? Build & Price Your Building

Common questions

Can I put a metal building on a slab I already have?

Sometimes. The slab has to be big enough, level, thick enough at the edges for the anchors, and match the building’s anchor drawings. Send us photos and the slab’s size and we will tell you whether it will work before you buy a building.

Do carports need footers?

Not always. Open carports on gravel or dirt often use ground anchors. If your county requires a permit, or the building is certified to a rating that calls for concrete, the drawings will say what the foundation needs.

Should I put a vapor barrier under my garage slab?

Virginia’s code does not require one under an unheated garage, but it is cheap insurance if you might heat, insulate or finish the space later. It also helps keep ground moisture from coming up through the floor.

What thickness slab do I need for heavy equipment?

A 4-inch slab handles most cars, trucks and shop use. Heavy equipment, point loads like a vehicle lift, or soft soil can call for a thicker or reinforced slab. See is a 4-inch slab enough.